The proposed Chewko Solar Farm is planned to be located eight kilometres south-west of Mareeba, Queensland.

The proposed solar farm will consist of about 200,000 solar PV panels and will be capable of delivering up to 75MW of renewable energy. It will be located on 150 hectares south-west of Mareeba on land that is currently used for grazing cattle.

The energy generated will be injected into the national electricity grid through an onsite connection that ties into the 132kv power line which runs between Turkinje and Yalkula.

Construction will take about 12 months, with about 250 people employed during the construction period and one to two people during the farm’s 25 years of operation. It will also provide an economic boost to supporting business and services within the Mareeba Shire Council.

A planning application for the project is expected to be lodged in September this year.

Download the Chewko Solar Farm fact sheet

 

Community Engagement

At Tilt Renewables we value the strong relationships we’ve shared with landowners and local community groups on all our projects and we would like to build on these relationships for the proposed Chewko Solar Farm as well.

We anticipate submitting a planning application for the project in September 2017. We will undertake community and stakeholder consultation to provide further  information and welcome any feedback on the proposal.

As part of this process we will offer to meet face to face with immediate neighbours and interested parties.

Tilt Renewables has implemented community benefit funds at most of our operating projects and we will be looking at establishing a similar scheme for this project once operational. We will engage with the local community closer to construction on an appropriate format and representative management committee for such a community fund.

 

Project News

Visit this page regularly to ensure you receive all news updates and promotional material related to the Chewko Solar Farm.

Newsletters

Newsletters are an important part of Tilt’s community engagement and will increase in frequency as the Project develops.

To subscribe to our newsletter mailing list, please click here.

 

 

Project Details

Location:
Mareeba, QLD

View Map

Installed Capacity
Up to 75MW

Solar panels
200,000

Project investment
Up to $100 million

Construction period
About 12 months

Project Status
Lodge planning application September 2017.

Environmental Benefits
The proposed project will provide enough clean energy to power 21,000 homes and save 100,000 tonnes of annual greenhouse gas emissions (equivalent of  removing 24,000 cars from the roads per year).

Employment
250 during construction and 1-2 during 25 years of operation.
 