Salt Creek Wind Farm - Construction Update #1

International turbine supplier Vestas and balance-of-plant contractor Zenviron have partnered in a consortium to build the Salt Creek Wind Farm. Site works will begin during September, with construction currently in the design planning stages. 

Various submissions have been collated in a Goods & Services Register which is being reviewed by the consortium, which may contract these goods and services. We thank everyone who attended the July Community Day, which distributed information about the project and updated interested locals on the process, with about 40 people calling in throughout the course of the day. 

The first major work will be the five kilometre Hexham/Woorndoo Road upgrade. This road work is a priority and is to be completed as soon as possible. While the road upgrade in occurring the site access road will commence, the site offices and various letdown areas will be installed, as well as the platforms for the operations and maintenance building and substation.

Regular updates will be made on this Project News section throughout the course of construction. If you have any queries please phone 1800 122 823 or email saltcreekwindfarm@tiltrenewables.com